The Woodsmith Project - S73 Project Amendments : Planning Statement
Condition Number
Current Wording
Proposed Amendment
Assessment informed by the most up-to-date monitoring, shall be submitted to the Local Planning Authority for approval in writing. Following approval of the Revised Hydro-geological Risk Assessment but prior to the commencement of development at Wilton, Lockwood Beck and Tocketts Lythe a Construction and Operation Phase Ground and Surface Water Monitoring Scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include:- • Groundwater quality and level triggers; • Surface water quality triggers; • Details of the number, type and location of monitoring points; • A protocol for the removal and replacement of any existing monitoring points; • Details of the frequency with which monitoring points will be monitored during construction and operation;
Amend condition to remove reference to Tocketts Lythe.
21
•
A list of the ground and surface water determinants to be tested for; Monitoring of groundwater levels and spring flows; Details of the method and frequency with which monitoring results will be shared with the Local Planning Authority and the Environment Agency
• •
The approved scheme shall thereafter be implemented in full, with monitoring continuing in accordance with the approved scheme until such time that it is agreed in writing with the Local Planning Authority that monitoring may cease. No development work that may impact on water resources receptors shall commence at Wilton, Lockwood Beck and Tocketts Lythe until a Remedial Action Plan, setting out the remedial actions to be taken in the event that any monitoring triggers are exceeded,
22
Amend condition to remove reference to Tocketts Lythe.
Pg 61
Powered by FlippingBook