The Woodsmith Project - S73 Project Amendments : Planning Statement
Condition Number
Current Wording
Proposed Amendment
C area shall be achieved in accordance with the approved details unless otherwise agreed in writing with the MPA.
permanent spoil mounding in the Bund C area (as defined on Figure 3-7 of the Supplementary Environmental Statement (Haskoning, March 2026 ) shall be submitted to the MPA for written approval and final ground levels in the Bund C area shall be achieved in accordance with the approved details unless otherwise agreed in writing with the MPA. To bring the date of production in line with how it is defined within the S106, the following revised wording is proposed: Means the date occurring after the construction period, determined as the latest of the following dates:
Glossary of Terms and
Means the date at which polyhalite is placed on the conveyor within the MTS on a continuous production basis other than polyhalite resulting from the construction of the chambers at the base of the shaft which are required to contain equipment and operations needed in support of subsequent ongoing mining operations.
Abbreviations Terms – Date of Production
i.
The removal of the temporary winding towers at DNF; One year after the completion of the tree planting, shrub planting and seeding of the bunds at DNF pursuant to conditions 57 and 71 of the NYMNPA Planning Permission; The MTS becoming operational; The date that the movement of polyhalite by road finally ceases; The removal of the temporary right hand turn lane at the shaft entrance to DNF
ii.
iii. iv.
v.
Means all above ground structures shown on the ‘Doves Nest Farm Proposed Site and Block Plan’ (Drawing No. 653-AP-0005 Rev 4) or
To reflect the updated plans, the following amended wording is proposed:
Glossary of Terms and Abbreviations
Pg 59