Report

Jacobs mobilisation to site including;

6

R/2019/0216/CD

22/05/2019

- Establishment of temporary access roads (one permanent), site boundaries, fencing, gates etc; - Ground preparation/foundations for temporary facilities, laydown areas, parking and walkways;

- Temporary utility services – potable water and sewage;

- Preparation for piling mat (i.e. ground levelling);

- Small power electrical temporary works including IT/Communications;

- Installation of temporary construction site accommodation including offices, welfare facilities, cabins, stores and security; and

Delivery of plant and materials.

-

Second storey to Strabag offices; and

• Drilling of four additional boreholes for monitoring

• Civils works (excavation) of the MHF RoM dome tunnel;

7

R/2019/0464/CD

11/09/2019

Piling works for MHF;

Site roads, access, drainage and utilities;

• Second storey to Strabag welfare facilities;

• Increase in the height of the existing MTS muck bin;

• Erection of temporary facility for the assembly of reinforcement cages; and

Attenuation pond for site drainage.

Erection of steelwork for RoM dome;

8

R/2021/0660/CD

23/09/2021

• Installation of foundations for MTS feed conveyor tower;

Pg 20/21 40864454v1