Jacobs mobilisation to site including;
6
R/2019/0216/CD
22/05/2019
•
- Establishment of temporary access roads (one permanent), site boundaries, fencing, gates etc; - Ground preparation/foundations for temporary facilities, laydown areas, parking and walkways;
- Temporary utility services – potable water and sewage;
- Preparation for piling mat (i.e. ground levelling);
- Small power electrical temporary works including IT/Communications;
- Installation of temporary construction site accommodation including offices, welfare facilities, cabins, stores and security; and
Delivery of plant and materials.
-
Second storey to Strabag offices; and
•
• Drilling of four additional boreholes for monitoring
• Civils works (excavation) of the MHF RoM dome tunnel;
7
R/2019/0464/CD
11/09/2019
Piling works for MHF;
•
Site roads, access, drainage and utilities;
•
• Second storey to Strabag welfare facilities;
• Increase in the height of the existing MTS muck bin;
• Erection of temporary facility for the assembly of reinforcement cages; and
Attenuation pond for site drainage.
•
Erection of steelwork for RoM dome;
8
R/2021/0660/CD
23/09/2021
•
• Installation of foundations for MTS feed conveyor tower;
Pg 20/21 40864454v1