Report

Installation and use of 40ft tally hut;

11

R/2022/0636/CD

26/09/2022

• Installation and use of temporary cable laying winch;

Installation of head house louvres;

Revision of haul road layout; and

Grout plant waste management facility.

MTS Portal

• Initial site works (scope as defined in the Phase 1 Works Drawing No. 40-HMJ-WI-2420-PA-22- 00001);

1

R/2017/0850/CD

20/01/2018

• Installation of site offices, maintenance sheds and stores, hoarding;

Delivery of plant and materials;

Trial holes;

Preparation of piling platform (partial);

• Platform construction, ground levelling, filling, compacting; and

Temporary electrical installations.

• Drainage works involving Mill Dyke and Mains Dyke, as per drawing 40-STR-WI-2400-PA-31- 12101; • Installation of guide walls and secant piled walls in preparation for the installation of the tunnel portal ramp, as per drawing 40-STR-WI-2400-PA-31-12101; • Installation of approximately 24 passive wells between the two secant pile walls for use in Phase 2; and

1a

R/2018/0297/CD

18/07/2018

• Extension of the Phase 1a enabling works platform.

• Site installation for Sprayed Concrete Lining (SCL) facilities;

2

R/2018/0411/CD

29/08/2018