Installation and use of 40ft tally hut;
11
R/2022/0636/CD
26/09/2022
•
• Installation and use of temporary cable laying winch;
Installation of head house louvres;
•
Revision of haul road layout; and
•
Grout plant waste management facility.
•
MTS Portal
• Initial site works (scope as defined in the Phase 1 Works Drawing No. 40-HMJ-WI-2420-PA-22- 00001);
1
R/2017/0850/CD
20/01/2018
• Installation of site offices, maintenance sheds and stores, hoarding;
Delivery of plant and materials;
•
Trial holes;
•
Preparation of piling platform (partial);
•
• Platform construction, ground levelling, filling, compacting; and
Temporary electrical installations.
•
• Drainage works involving Mill Dyke and Mains Dyke, as per drawing 40-STR-WI-2400-PA-31- 12101; • Installation of guide walls and secant piled walls in preparation for the installation of the tunnel portal ramp, as per drawing 40-STR-WI-2400-PA-31-12101; • Installation of approximately 24 passive wells between the two secant pile walls for use in Phase 2; and
1a
R/2018/0297/CD
18/07/2018
• Extension of the Phase 1a enabling works platform.
• Site installation for Sprayed Concrete Lining (SCL) facilities;
2
R/2018/0411/CD
29/08/2018