Report

• Installation of grout shed and air compressor shed;

• Minor extension of existing working platform; and

Installation of pump unit.

• Mobilisation of shaft sinking contractors, including establishment of temporary welfare facilities, installation of shaft sinking equipment and shaft platform civils and infrastructure;

8

R/2020/0415/CD

28/09/2020

• Construction of cuttings lagoon on the surface of the existing pad;

• Dismantling of temporary head frame tower structure over existing MTS shaft;

• Sinking of alternative MTS shaft via drill boring method; and

Partial remediation of the existing shaft.

• The backfilling of the existing cuttings lagoon and its reinstatement as part of the working platform;

9

R/2021/0800/CD

15/11/2021

• The installation of a transformer and substation; and

• The addition of a tally hut and ventilation fan for the shaft.

• Installation and use of temporary shaft head house;

10

R/2021/0945/CD

04/02/2022

• Installation and use of grout plant and associated services;

• Construction and use of adit connection to the MTS shaft;

Establishment of tarmac haul road; and

• Revised specification of transformer and substation compound.

Relocation of the grout plant;

10a

R/2022/0317/CD

27/05/2022

• Additional units within the grout plant footprint;

• Construction of a wedge pit within the grout plant footprint; and

Re-design of the temporary headhouse.

Pg 17/21 40864454v1