• Contractor mobilisation (temporary warehouse, mechanical shop and electrical shop);

4

R/2018/0560/CD

30/10/2018

• Temporary excavation and pile cropping (to 183mAoD);

• Shaft excavation, capping beam and collar construction;

Headframe and Winder building – foundations and structure construction;

Galloway delivery;

• Access road and Secure Storage Unit (SSU) topsoil removal, ducting and fencing;

• Earthworks for access road and SSU bunding, including landscaping;

• Construction of road extension and SSU platform;

SSU installation; and

• Construction of Site Eye camera frame base.

Operation of Secure Storage Unit (SSU);

5

R/2018/0675/CD

19/12/2018

• Excavation of foreshaft using longboom method;

• Pre-Sink to approximately 128m AoD, using a mini-excavator and crane much buckets;

• Galloway construction, assembly and fit out; and

• Minor alterations and extension of existing working platform.

• Installation and operation of non-domestic wastewater treatment plant; and

6

R/2019/0059/CD

29/03/2019

• Installation and operation of the compressed air unit.

• Sinking of MTS shaft via drill and blast method;

7

R/2019/0499/CD

11/09/2019

Extractive material management;

Operation of Galloway;

• Installation and operation of concrete batching plant;