Report

• Provision of culvert crossing Lockwood Beck; and

• Limited landscaping, mainly seeding of spoil mounds.

Site mobilisation;

3

R/2017/0784/CD

12/01/2018

Installation of site welfare;

Installation of High Voltage equipment;

• Excavation of freeze cellars to -5m below platform level (bpl);

• Construction of a circular secant pile wall to -30m bpl;

Construction of freeze cellar structure;

• Construction of a cover for the freeze cellar with a reinforced concrete slab and backfill around the outer freeze cellar walls;

Drilling of freeze holes to -160m bpl;

• Installation and commissioning of the in-ground freeze pipes, piping instrumentation and the freeze plant; • Ground freeze to -160m bpl (a depth immediately below the identified water bearing geological units);

Pre-sink to -30m bpl; and

Installation of surface level civils;

Winder foundations and slabs; and

-

Headframe foundations and slabs.

-

• Installation of thin walled reservation tubes to 173.09m AOD, to enable grouting works;

3a

R/2018/0354/CD

29/08/2018

Drilling and Grouting to 28.09m AOD; and

• Installation of the NPG kiosk at the site entrance.