Report

• Excavation of Service Shaft via a mechanical extraction method;

10

NYM/2019/0203/CVC

30/04/2019

• Installation of grout shed and air compressor;

• Erection of temporary storage unit for winder equipment;

• Installation of drying rooms adjacent to the existing welfare facility; and

Installation of oxygen tank and cabin.

• Development of landscape mitigation screening;

11

NYM/2019/0524/CVC

11/11/2019

Tree clearance within Haxby plantation;

• Sinking of the MTS shaft via drill and blast method;

Operation of the Galloway;

Creation of a materials handling area;

• Installation of external silencer to the dust collector of the Service Shaft building; and

Installation of batteries.

• Assembly and operation of Shaft Boring Roadheaders (SBRs) at both Service Shaft and Production Shaft;

12

NYM/2020/0259/CVC

15/06/2020

Installation of additional welfare cabins;

• Installation of segregated materials bunker;

• Creation of laydown area for segment and tubbing storage;

• Installation of lightning protection and canopy to Secure Storage Units (SSUs); and

Installation of access control measures.

• Establishment and use of temporary laydown area for storage of segments;

13

NYM/2021/0037/CVC

19/04/2021

• Construction and use of secondary secure storage unit;