Report

• Reticulation of mains power from Northern Powergrid kiosk;

6

NYM/2018/0401/CVC

07/08/2018

• Construction of temporary secure storage unit;

• Civils work to construct an access road, pad and associated drainage in a previously cleared area within Haxby Plantation; and

Second level of welfare buildings.

• Installation and operation of a Liquified Natural Gas (LNG) plant.

6a

NYM/2018/0663/CVC

25/01/2019

• Completion of Service Shaft headgear chamber;

7

NYM/2018/0585/CVC

19/11/2018

• Completion of Service Shaft to 83.17m AoD via VSM method;

• Excavation of Production Shaft headgear chamber;

• Excavation from base of Production Shaft headgear chamber to 83.66m AoD;

• LNG generation plant mechanical and electrical fit out;

• Surface water run-off silt treatment facility building;

• Erection of temporary facilities to enable mobilisation of deep shaft sinking contractor;

Earthworks and drainage; and

Contingency grouting of the MTS Shaft.

• Construction of permanent Service Shaft building, including installation of winder equipment; and

8

NYM/2018/0771/CVC

05/04/2019

• Construction of permanent Production Shaft building, including installation of winder equipment.

• Installation and operation of temporary Secure Storage Unit (SSU);

9

NYM/2019/0041/CVC

29/03/2019

• Installation and operation of non-domestic wastewater treatment plant;

• Installation and commissioning of compressors; and

Assembly and fit-out of Galloway.