Report

• Site works to allow the construction of a right-hand turn off the A171; and

1

NYM/2021/0087/CVC

07/04/2021

Creation of a safe site entrance.

• Topsoil and subsoil strip and creation of storage/screening mounds to the north of site;

2

NYM/2021/0581/CVC

06/09/2021

Preparation of haul roads;

• Preparation of drill pad and laydown areas;

• Preparation of drainage in the form of an attenuation pond and swales for surface water control; and

• Installation of security gatehouse, fencing and barriers.

• Additional soil stripping and storage within temporary bunds;

3

NYM/2021/1015/CVC

04/02/2022

• Installation and use of hardstanding for welfare, car parking and laydown areas;

Installation of foul drainage facilities;

• Installation of further site surface water drainage, including oil interceptor;

• Mobilisation of on-site facilities, including welfare, car park, wheel wash, refuelling, workshop, grout plant and associated services;

• Construction of cuttings lagoon and associated cuttings pit and muck away; and

• Installation of working pad for pre-grouting and shaft sinking works.

• Redesign, and change to construction methodology, of the cuttings lagoon as previously approved under Phase 3. • Installation and use of site utilities including water supply, electric supply, substation and transformer;

3a

NYM/2022/0346

13/06/2022

4

NYM/2022/0286

26/05/2022

• Extension of working pad for grout plant and installation of wedge pit;

Pg 12/21 40864454v1