Proposed Minehead - Existing Landscape Features Proposed Minehead - Removal of Existing Landscape Features Proposed Minehead - Restoration Proposals Proposed Minehead - Restoration Proposals - Cross Sections Proposed Minehead - Restoration Proposals - Cross Sections Proposed Minehead - Restoration Proposals - Cross Sections Tree protection measures for works in highways at A171/B1416 right turn Mine head Site Welfare Entrance General Arrangement (From ES Appendix 3.3) Proposed Mine and MTS Sub-Surface Structures
2309.MH01 rev 04
Delete plan – no longer relevant, following construction activity.
2309.MH02 rev 04
No change.
2309.MH03 rev 07
Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement. Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement. Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement. Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement.
2309.MH04 rev 06
2309.MHOS rev 06
2309.MH06 rev 06
2556.473.AIA.Whitby. YPL
Delete plan – works have been completed.
YP-P2-CX-043 Issue 0
Delete plan – no longer relevant given the proposed relocation of the welfare facility.
40-SMP-WS-1400-PA-31-00001 rev. A
Woodsmith Project - Woodsmith Site Revision F Mine Plan Isometric View
1000-WOB-PA-31-00001 A
(NB. Drawing approved under S96a approval ref. NYM/2018/0470/NM).
Woodsmith Project - Woodsmith Site Secure Storage Units A and B Floor Plan and Elevations Woodsmith Project - Woodsmith Site Secure Storage Area and SSU C Floor Plan and Elevations Woodsmith Project - Woodsmith Site NPG Kiosk Floor Plan and Elevations
New plan
N/A
1520-WOB-PA-31-00001 D
New plan
N/A
1520-WOB-PA-31-00002 C
New plan
N/A
1561-WOB-PA-31-00003 B