Report

Proposed Minehead - Existing Landscape Features Proposed Minehead - Removal of Existing Landscape Features Proposed Minehead - Restoration Proposals Proposed Minehead - Restoration Proposals - Cross Sections Proposed Minehead - Restoration Proposals - Cross Sections Proposed Minehead - Restoration Proposals - Cross Sections Tree protection measures for works in highways at A171/B1416 right turn Mine head Site Welfare Entrance General Arrangement (From ES Appendix 3.3) Proposed Mine and MTS Sub-Surface Structures

2309.MH01 rev 04

Delete plan – no longer relevant, following construction activity.

2309.MH02 rev 04

No change.

2309.MH03 rev 07

Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement. Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement. Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement. Delete plan – indicative restoration details and plans are included within the Supplementary Environmental Statement.

2309.MH04 rev 06

2309.MHOS rev 06

2309.MH06 rev 06

2556.473.AIA.Whitby. YPL

Delete plan – works have been completed.

YP-P2-CX-043 Issue 0

Delete plan – no longer relevant given the proposed relocation of the welfare facility.

40-SMP-WS-1400-PA-31-00001 rev. A

Woodsmith Project - Woodsmith Site Revision F Mine Plan Isometric View

1000-WOB-PA-31-00001 A

(NB. Drawing approved under S96a approval ref. NYM/2018/0470/NM).

Woodsmith Project - Woodsmith Site Secure Storage Units A and B Floor Plan and Elevations Woodsmith Project - Woodsmith Site Secure Storage Area and SSU C Floor Plan and Elevations Woodsmith Project - Woodsmith Site NPG Kiosk Floor Plan and Elevations

New plan

N/A

1520-WOB-PA-31-00001 D

New plan

N/A

1520-WOB-PA-31-00002 C

New plan

N/A

1561-WOB-PA-31-00003 B

40945451v1