Report

Mine Building 07 - Men and Material Shaft Winder Plan, Section and Elevations - Colour

DMC-WS-P-0150-1100-AR-DR11-2170 rev. J

Woodsmith Project - Woodsmith Site Service Shaft Floor and Roof Plan Woodsmith Project - Woodsmith Site Service Shaft Elevations – Sheet 1 Woodsmith Project - Woodsmith Site Service Shaft Elevations - Sheet 2 Woodsmith Project - Woodsmith Site Production Shaft Floor and Roof Plan Woodsmith Project - Woodsmith Site Production Shaft Elevations - Sheet 1 Woodsmith Project - Woodsmith Site Production Shaft Elevations - Sheet 2 Woodsmith Site Bulk Air Cooler Floor Plan and Elevations

1221-WOB-PA-31-00009 E

(NB. Drawing approved under S96a approval ref. NYM/2019/0129/NM).

1221-WOB-PA-31-00010 F

1221-WOB-PA-31-00011 E

Mine Building 08 - Mineral Shaft Winder Plan, Section and Elevations - Colour

DMC-WS-P-0150-1200-AR-DR11-2171 rev. P

1121-WOB-PA-31-00009 D

(NB. Drawing approved under S96a approval ref. NYM/2019/0129/NM).

1121-WOB-PA-31-00010 D

1121-WOB-PA-31-00011 D

Mine Building 09 - MTS Shaft Building Plan, Section and Elevations - Colour

653-AP-0056 rev 6

1321-WOB-PA-31-00001 C

Mine Building - Elevation Study - Colour

653-AP-0058 rev 10

Delete plan – refer to detail shown on elevation drawings.

(NB. Drawing approved under S96a approval ref. NYM/2019/0129/NM).

Doves Nest Farm - Existing Site Sections Sheet 01 Doves Nest Farm - Existing Site Sections Sheet 02

653-AP-0003 rev 0

Delete plan – no longer relevant, following construction activity.

653-AP-0004 rev 0

Delete plan – no longer relevant, following construction activity.

Doves Nest Farm - Proposed Site Sections Sheet 01

653-AP-0008 rev 3

Woodsmith Site Operational Earthworks Site Sections Sheet 1

1500-ARI-PA-10-01007 E

40945451v1