The Woodsmith Project - S73 Project Amendments : Planning Statement
Condition Number
Current Wording
Proposed Amendment
The approved measures shall be brought into operation and maintained to the satisfaction of the MPA in accordance with the approved details.
evidence, together with the evidence to demonstrate a lack of presence of groundwater-dependent habitat, justifies removal of the requirement for the recharge trench. Part b) should be retained but should only reference bund F (on the basis that there is no longer a bund E proposed). Delete condition to reflect completion of surveys and subsequent approval of these details under NYM/2025/0433.
Breeding birds surveys of the wooded heath north of Lady Cross Plantation to identify the extent of its use as breeding habitat by nightjar must be undertaken and completed prior to the Commencement of Development at the Lady Cross Plantation site. Before the results of these surveys are known, noise emitted within the breeding season 15 May to 30 September inclusive must be controlled to levels that would not disturb nightjar breeding on the wooded heath north of Lady Cross Plantation. Should the surveys indicate the presence of nightjar breeding on wooded heath north of Lady Cross Plantation, mitigation measures must be agreed with the MPA and be implemented before noise at levels likely to disturb nightjar during the breeding season 15 May to 30 September inclusive is emitted from development at the Lady Cross Plantation site. The survey methodology shall be agreed with the MPA in advance of the surveys being undertaken. Schemes shall be put in place to avoid damage to species rich grassland in roadside verges in the vicinity of Doves Nest Farm and Lady Cross Plantation and Preparatory Works shall not be allowed to commence until these schemes have been established and agreed in writing by the MPA. The schemes shall cover the construction periods and shall identify precisely the species rich grassland roadside verge areas covered by the schemes and the means by which damage shall be avoided, and shall include provision for
55
56
Delete condition to reflect the previous discharge of this condition under NYM/2025/0433 and subsequent completion of works.
Pg 55