The Woodsmith Project - S73 Project Amendments : Planning Statement
Condition Number
Current Wording
Proposed Amendment
The notification shall include the following: • Location of the blast site; • Approximate times of blasting; and • Details of any warnings to be given prior to blasting. Blasting operations shall be carried out in accordance with the blasting schedule. Any changes to the schedule arising through exceptional circumstances must be notified in writing with the MPA. Prior to any off-site highways works requiring a TRO, details of the following Traffic Regulation Orders (TROs) shall have been submitted to and approved in writing by the MPA in consultation with the Highway Authority: • A "clearway" order along the 81416 in the vicinity of the Doves Nest Farm access and secondary construction access;
37
Delete condition to reflect the previous discharge of this condition under NYM/2016/0305/CVC and subsequent completion of these works.
• •
Temporary speed limits during construction; and
TROs related to the proposed off site highway works. The approved details shall, at the applicant's expense, undergo the legal process required. Subject to the successful completion of this legal process the measures will be implemented at the applicant's cost according to a timetable to be approved in writing by the MPA in consultation with the Highway Authority. Within six months of the date of this permission, a programme for the delivery of the off-site highway works shall be submitted to and approved in writing by the MPA in consultation with the Highway Authority. The programme shall have regard to the level of construction employee traffic, HGV deliveries, and base flow traffic movements. It shall include the timing of:- • Submissions of detailed designs and all construction documentation for the off-site highway works for approval;
39
Amend condition to reflect that all the off-site highways works have been completed, with only Normanby Bends outstanding (if required). Suggested alternative wording as follows: Prior to the Date of Production, a Road Safety Study relating to the section of the A171 known as Normanby Bends (between the grid reference points NZ929072 and NZ927059) shall be submitted in writing to the Mineral Planning
Pg 52