Report

Proposed Site Plan

653-LC-AP-0203 rev 2

Plan deleted – detail shown on Ladycross Site – Operational Masterplan - 2300-ARI-PA-18-01000 E

Proposed Compound Site Plan and Block Plan

653-LC-AP-0204 rev 2

Ladycross Site - Proposed Operational Compound Site Plan and Block Plan Ladycross Site - Operational Earthworks Site Sections Woodsmith Project - Ladycross Site - Site Layout Plan and Indicative 3D View Woodsmith Project - Ladycross Site Head House Floor and Roof Plans Woodsmith Project - Ladycross Site Head House Elevations Ladycross Site - Operational Hard and Soft Landscaping Plan

2300-ARI-PA-18-01005 E

Proposed Site Sections

653-LC-AP-0205 rev 0

2300-ARI-PA-10-01007 E

MTS Building Proposed Plan, Section and Elevations

653-LC-AP-0207 rev 0

2320-WOB-PA-31-00001 C

2320-WOB-PA-31-00002 B

2320-WOB-PA-31-00003 B

Proposed Hard Landscaping Plan

653-LC-AP-0208 rev 3

2300-ARI-PA-18-01008 E

Proposed Site Earthworks - Ladycross Plantation, Spoil Phasing

YP-P2-CX-443 rev 7

Plan to be deleted – no longer relevant due to removal of landfill from proposed development Plan to be deleted – refer to Ladycross Site Operational Drainage General Arrangement (ref. 2300-ARI-PA-18-01010 E) Plan to be deleted – details have been superseded by construction activity Plan to be deleted – details have been superseded by construction activity Plan to be deleted – no longer relevant due to removal of landfill from proposed development Plan to be deleted - details have been superseded by construction activity.

Drainage working plan

YP-P2-CX-528 rev 2

Proposed Phasing Strategy: Phases 1 - 5

40-SMP-LC-8600-LP-31-00001 rev. 0

(NB. Drawing approved under s96a approval ref. NYM/2019/0805/NM).

Proposed Phasing Strategy: Phase 6

YP-P2-CX-543 rev 2

Working Plan: General Arrangement and Earthworks

YP-P2-CX-525 rev 2

Ladycross Plantation Drainage - Construction

YP-P2-CX-445 rev 7

40945451v1